Power now
130 MW
Load
61% of 210 MW
Running without a break
9 days, since 9 Nov 2026
Last 24 hours
Unit output, MW, every 15 minutes
maximum power 210 MW
now 130 MW
Operating history
The selected period applies to the operating strip and daily energy: 20 Oct – 18 Nov 2026
Operation and stops
In operation on 25 of 30 days
The value is the unit's average load over the day as a percentage of its maximum power; below 60% means running at reduced power.
| Day | LZA32S11 |
|---|---|
| 18 Nov 2026 | 61% |
| 17 Nov 2026 | 66% |
| 16 Nov 2026 | 64% |
| 15 Nov 2026 | 61% |
| 14 Nov 2026 | 62% |
| 13 Nov 2026 | 65% |
| 12 Nov 2026 | 63% |
| 11 Nov 2026 | 68% |
| 10 Nov 2026 | 70% |
| 9 Nov 2026 | 48% |
| 8 Nov 2026 | stopped |
| 7 Nov 2026 | stopped |
| 6 Nov 2026 | 74% |
| 5 Nov 2026 | 72% |
| 4 Nov 2026 | 65% |
| 3 Nov 2026 | 61% |
| 2 Nov 2026 | 54% |
| 1 Nov 2026 | stopped |
| 31 Oct 2026 | stopped |
| 30 Oct 2026 | 68% |
| 29 Oct 2026 | 69% |
| 28 Oct 2026 | 66% |
| 27 Oct 2026 | 64% |
| 26 Oct 2026 | 62% |
| 25 Oct 2026 | stopped |
| 24 Oct 2026 | 22% |
| 23 Oct 2026 | 64% |
| 22 Oct 2026 | 62% |
| 21 Oct 2026 | 27% |
| 20 Oct 2026 | 36% |
stoppedrunning below 60% of max powerrunning at 60% or more
Daily energy
MWh per day. Select a day to see its profile.
selected day: Tuesday 17 Nov 2026 · 3,300 MWh
Day profile
Tuesday 17 Nov 2026, MW
Outages in the last 12 months
Lasting at least a day, most recent first
Time in operation
66.1%
Outages in total
89 days
| Start | End | Length | Label |
|---|---|---|---|
| 6 Nov 2026 23:45 | 9 Nov 2026 04:00 | 2 days | |
| 31 Oct 2026 00:00 | 2 Nov 2026 03:00 | 2 days | |
| 24 Oct 2026 22:15 | 26 Oct 2026 00:00 | 1 day | |
| 17 Oct 2026 00:00 | 19 Oct 2026 04:45 | 2 days | |
| 8 Oct 2026 19:30 | 12 Oct 2026 04:15 | 3 days | |
| 26 Sep 2026 00:00 | 29 Sep 2026 04:00 | 3 days | |
| 19 Sep 2026 00:00 | 21 Sep 2026 04:45 | 2 days | |
| 5 Sep 2026 22:15 | 7 Sep 2026 02:15 | 1 day | |
| 4 Sep 2026 01:15 | 5 Sep 2026 06:30 | 1 day | |
| 28 Aug 2026 21:15 | 30 Aug 2026 23:45 | 2 days | |
| 22 Aug 2026 09:00 | 24 Aug 2026 02:00 | 1 day | |
| 7 Aug 2026 22:30 | 10 Aug 2026 15:30 | 2 days | |
| 5 Aug 2026 08:15 | 6 Aug 2026 15:30 | 1 day | |
| 1 Aug 2026 03:15 | 3 Aug 2026 13:30 | 2 days | |
| 27 Jul 2026 02:00 | 31 Jul 2026 16:45 | 4 days | |
| 24 Jul 2026 03:45 | 25 Jul 2026 12:15 | 1 day | |
| 21 Jul 2026 23:15 | 23 Jul 2026 18:15 | 1 day | |
| 17 Jul 2026 00:15 | 20 Jul 2026 14:45 | 3 days | |
| 26 Jun 2026 21:30 | 29 Jun 2026 05:30 | 2 days | |
| 15 Jun 2026 22:15 | 18 Jun 2026 03:00 | 2 days | |
| 12 Jun 2026 00:00 | 15 Jun 2026 05:00 | 3 days | |
| 19 May 2026 09:00 | 26 May 2026 03:30 | 6 days | |
| 7 May 2026 08:30 | 18 May 2026 15:15 | 11 days | longer outage |
| 27 Apr 2026 22:00 | 2 May 2026 04:45 | 4 days | |
| 24 Apr 2026 00:00 | 25 Apr 2026 05:30 | 1 day | |
| 18 Apr 2026 00:00 | 20 Apr 2026 02:00 | 2 days | |
| 12 Apr 2026 22:30 | 14 Apr 2026 03:00 | 1 day | |
| 4 Apr 2026 00:00 | 7 Apr 2026 20:30 | 3 days | |
| 28 Mar 2026 00:00 | 31 Mar 2026 01:00 | 3 days | |
| 13 Mar 2026 23:00 | 16 Mar 2026 02:45 | 2 days | |
| 26 Feb 2026 20:30 | 2 Mar 2026 12:15 | 3 days | |
| 21 Feb 2026 22:00 | 23 Feb 2026 03:15 | 1 day |
A unit is stopped when its output falls to 2% of its maximum power or less (at least 5 MW); breaks shorter than an hour are merged. Maximum power is the highest output observed in the last 12 months. Scale: 7–13 days is a longer outage, 14–29 days a long one, 30 days or more a very long one.