The Watt Mix
PLEN
Archived data: PSE has not reported this unit since 31 Jan 2026
Hard coal unit

JW2_4-07

plant: Jaworzno 2 JWCD · operator: Tauron Wytwarzanie

Operating history

The selected period applies to the operating strip and daily energy: 2 Jan – 31 Jan 2026
All

Operation and stops

In operation on 27 of 30 days
stoppedrunning below 60% of max powerrunning at 60% or more

Daily energy

MWh per day. Select a day to see its profile.
selected day: Saturday 31 Jan 2026 · 10,500 MWh

Day profile

Saturday 31 Jan 2026, MW

Outages in the last 12 months

Lasting at least a day, most recent first
Time in operation
90.2%
Outages in total
7 days
StartEndLengthLabel
16 Jan 2026 19:4520 Jan 2026 01:003 days
5 Dec 2025 04:459 Dec 2025 05:304 days
A unit is stopped when its output falls to 2% of its maximum power or less (at least 5 MW); breaks shorter than an hour are merged. Maximum power is the highest output observed in the last 12 months. Scale: 7–13 days is a longer outage, 14–29 days a long one, 30 days or more a very long one.