Archived data: PSE has not reported this unit since 31 Jan 2026
Hard coal unit

LZA31-10

plant: Łaziska 3 · operator: Tauron Wytwarzanie

Operating history

The selected period applies to the operating strip and daily energy: 2 Jan – 31 Jan 2026
All

Operation and stops

In operation on 0 of 30 days
stoppedrunning below 60% of max powerrunning at 60% or more

Daily energy

MWh per day. Select a day to see its profile.
selected day: Saturday 31 Jan 2026 · 0 MWh

Day profile

Saturday 31 Jan 2026, MW

Outages in the last 12 months

Lasting at least a day, most recent first
Time in operation
32.2%
Outages in total
50 days
StartEndLengthLabel
31 Dec 2025 23:45at least until 1 Feb 2026 00:00at least 31 daysvery long outage
18 Dec 2025 21:0031 Dec 2025 05:0012 dayslonger outage
12 Dec 2025 22:0015 Dec 2025 02:452 days
9 Dec 2025 22:0011 Dec 2025 13:151 day
7 Dec 2025 00:008 Dec 2025 03:001 day
29 Nov 2025 22:151 Dec 2025 04:451 day
A unit is stopped when its output falls to 2% of its maximum power or less (at least 5 MW); breaks shorter than an hour are merged. Maximum power is the highest output observed in the last 12 months. Scale: 7–13 days is a longer outage, 14–29 days a long one, 30 days or more a very long one.