Archived data: PSE has not reported this unit since 31 Aug 2026
Operating history
The selected period applies to the operating strip and daily energy: 2 Aug – 31 Aug 2026
Operation and stops
In operation on 21 of 30 days
The value is the unit's average load over the day as a percentage of its maximum power; below 60% means running at reduced power.
| Day | RYB 2-05 |
|---|---|
| 31 Aug 2026 | 75% |
| 30 Aug 2026 | 63% |
| 29 Aug 2026 | 71% |
| 28 Aug 2026 | 66% |
| 27 Aug 2026 | 61% |
| 26 Aug 2026 | 61% |
| 25 Aug 2026 | 62% |
| 24 Aug 2026 | 50% |
| 23 Aug 2026 | stopped |
| 22 Aug 2026 | stopped |
| 21 Aug 2026 | 38% |
| 20 Aug 2026 | 38% |
| 19 Aug 2026 | 63% |
| 18 Aug 2026 | 62% |
| 17 Aug 2026 | 21% |
| 16 Aug 2026 | stopped |
| 15 Aug 2026 | stopped |
| 14 Aug 2026 | stopped |
| 13 Aug 2026 | 55% |
| 12 Aug 2026 | 60% |
| 11 Aug 2026 | 60% |
| 10 Aug 2026 | 22% |
| 9 Aug 2026 | 17% |
| 8 Aug 2026 | stopped |
| 7 Aug 2026 | 47% |
| 6 Aug 2026 | 19% |
| 5 Aug 2026 | stopped |
| 4 Aug 2026 | 8% |
| 3 Aug 2026 | stopped |
| 2 Aug 2026 | stopped |
stoppedrunning below 60% of max powerrunning at 60% or more
Daily energy
MWh per day. Select a day to see its profile.
selected day: Monday 31 Aug 2026 · 3,800 MWh
Day profile
Monday 31 Aug 2026, MW
Outages in the last 12 months
Lasting at least a day, most recent first
Time in operation
72.3%
Outages in total
61 days
| Start | End | Length | Label |
|---|---|---|---|
| 21 Aug 2026 21:15 | 24 Aug 2026 05:00 | 2 days | |
| 13 Aug 2026 21:15 | 17 Aug 2026 14:00 | 3 days | |
| 7 Aug 2026 19:00 | 9 Aug 2026 14:30 | 1 day | |
| 4 Aug 2026 19:00 | 6 Aug 2026 15:00 | 1 day | |
| 31 Jul 2026 23:15 | 4 Aug 2026 14:30 | 3 days | |
| 23 Jul 2026 19:45 | 30 Jul 2026 13:15 | 6 days | |
| 9 Jul 2026 22:15 | 14 Jul 2026 03:30 | 4 days | |
| 6 Jul 2026 22:00 | 8 Jul 2026 14:30 | 1 day | |
| 4 Jul 2026 00:15 | 6 Jul 2026 03:15 | 2 days | |
| 27 Jun 2026 00:00 | 29 Jun 2026 14:30 | 2 days | |
| 23 May 2026 22:15 | 25 May 2026 14:30 | 1 day | |
| 16 May 2026 22:15 | 19 May 2026 04:15 | 2 days | |
| 8 May 2026 20:30 | 12 May 2026 03:45 | 3 days | |
| 14 Apr 2026 18:00 | 18 Apr 2026 04:00 | 3 days | |
| 10 Apr 2026 20:15 | 14 Apr 2026 04:15 | 3 days | |
| 12 Mar 2026 23:00 | 16 Mar 2026 03:15 | 3 days | |
| 16 Jan 2026 22:15 | 19 Jan 2026 03:30 | 2 days | |
| 25 Dec 2025 22:15 | 29 Dec 2025 03:30 | 3 days | |
| 19 Dec 2025 00:00 | 25 Dec 2025 14:30 | 6 days | |
| before 19 Nov 2025 00:00 | 20 Nov 2025 13:15 | at least 1 day |
A unit is stopped when its output falls to 2% of its maximum power or less (at least 5 MW); breaks shorter than an hour are merged. Maximum power is the highest output observed in the last 12 months. Scale: 7–13 days is a longer outage, 14–29 days a long one, 30 days or more a very long one.