live · 10:45 CET
PLEN
Hard coal unit

JW3_2S06

plant: Jaworzno 3 · operator: Tauron Wytwarzanie
Power now
0 MW
Load
0% of 210 MW
Not running
48 days, since 1 Oct 2026
very long outage

Last 24 hours

Unit output, MW, every 15 minutes
maximum power 210 MW
now 0 MW

Operating history

The selected period applies to the operating strip and daily energy: 20 Oct – 18 Nov 2026
All

Operation and stops

In operation on 0 of 30 days
stoppedrunning below 60% of max powerrunning at 60% or more

Daily energy

MWh per day. Select a day to see its profile.
selected day: Tuesday 17 Nov 2026 · 0 MWh

Day profile

Tuesday 17 Nov 2026, MW

Outages in the last 12 months

Lasting at least a day, most recent first
Time in operation
28.1%
Outages in total
203 days
StartEndLengthLabel
1 Oct 2026 00:00ongoing 48 daysvery long outage
11 Sep 2026 04:4514 Sep 2026 02:152 days
5 Sep 2026 16:157 Sep 2026 04:301 day
29 Aug 2026 01:3031 Aug 2026 15:002 days
7 Aug 2026 22:009 Aug 2026 15:301 day
1 Aug 2026 00:003 Aug 2026 14:152 days
27 Jul 2026 18:4531 Jul 2026 04:003 days
9 Jul 2026 23:3026 Jul 2026 08:0016 dayslong outage
20 Apr 2026 18:456 Jul 2026 05:0076 daysvery long outage
2 Apr 2026 23:4520 Apr 2026 09:1517 dayslong outage
24 Mar 2026 01:151 Apr 2026 02:158 dayslonger outage
21 Mar 2026 00:0022 Mar 2026 19:451 day
11 Mar 2026 23:0016 Mar 2026 15:004 days
26 Feb 2026 10:302 Mar 2026 13:304 days
23 Feb 2026 22:0025 Feb 2026 19:451 day
10 Feb 2026 12:3017 Feb 2026 04:006 days
6 Feb 2026 19:307 Feb 2026 19:451 day
before 1 Feb 2026 00:002 Feb 2026 12:30at least 1 day
A unit is stopped when its output falls to 2% of its maximum power or less (at least 5 MW); breaks shorter than an hour are merged. Maximum power is the highest output observed in the last 12 months. Scale: 7–13 days is a longer outage, 14–29 days a long one, 30 days or more a very long one.