Power now
190 MW
Load
52% of 360 MW
Running without a break
22 days, since 26 Oct 2026
Last 24 hours
Unit output, MW, every 15 minutes
maximum power 360 MW
now 190 MW
Operating history
The selected period applies to the operating strip and daily energy: 20 Oct – 18 Nov 2026
Operation and stops
In operation on 28 of 30 days
The value is the unit's average load over the day as a percentage of its maximum power; below 60% means running at reduced power.
| Day | BEL 4-11 |
|---|---|
| 18 Nov 2026 | 57% |
| 17 Nov 2026 | 98% |
| 16 Nov 2026 | 92% |
| 15 Nov 2026 | 62% |
| 14 Nov 2026 | 76% |
| 13 Nov 2026 | 81% |
| 12 Nov 2026 | 93% |
| 11 Nov 2026 | 61% |
| 10 Nov 2026 | 99% |
| 9 Nov 2026 | 97% |
| 8 Nov 2026 | 80% |
| 7 Nov 2026 | 70% |
| 6 Nov 2026 | 98% |
| 5 Nov 2026 | 94% |
| 4 Nov 2026 | 98% |
| 3 Nov 2026 | 97% |
| 2 Nov 2026 | 98% |
| 1 Nov 2026 | 85% |
| 31 Oct 2026 | 95% |
| 30 Oct 2026 | 98% |
| 29 Oct 2026 | 99% |
| 28 Oct 2026 | 95% |
| 27 Oct 2026 | 77% |
| 26 Oct 2026 | 9% |
| 25 Oct 2026 | stopped |
| 24 Oct 2026 | stopped |
| 23 Oct 2026 | 86% |
| 22 Oct 2026 | 91% |
| 21 Oct 2026 | 92% |
| 20 Oct 2026 | 98% |
stoppedrunning below 60% of max powerrunning at 60% or more
Daily energy
MWh per day. Select a day to see its profile.
selected day: Tuesday 17 Nov 2026 · 8,600 MWh
Day profile
Tuesday 17 Nov 2026, MW
Outages in the last 12 months
Lasting at least a day, most recent first
Time in operation
79.3%
Outages in total
68 days
| Start | End | Length | Label |
|---|---|---|---|
| 23 Oct 2026 23:45 | 26 Oct 2026 19:00 | 2 days | |
| 16 Oct 2026 23:45 | 19 Oct 2026 02:00 | 2 days | |
| 4 Oct 2026 00:00 | 5 Oct 2026 04:15 | 1 day | |
| 16 Sep 2026 19:00 | 21 Sep 2026 16:00 | 4 days | |
| 29 Aug 2026 00:00 | 30 Aug 2026 15:30 | 1 day | |
| 9 Aug 2026 00:00 | 22 Aug 2026 19:15 | 13 days | longer outage |
| 27 Jul 2026 04:00 | 28 Jul 2026 16:00 | 1 day | |
| 7 Jul 2026 00:15 | 9 Jul 2026 14:00 | 2 days | |
| 3 Jul 2026 08:15 | 6 Jul 2026 05:00 | 2 days | |
| 7 Jun 2026 00:00 | 10 Jun 2026 04:00 | 3 days | |
| 1 May 2026 00:00 | 4 May 2026 15:00 | 3 days | |
| 18 Apr 2026 00:00 | 19 Apr 2026 21:30 | 1 day | |
| 4 Apr 2026 02:30 | 7 Apr 2026 14:00 | 3 days | |
| 23 Mar 2026 04:00 | 26 Mar 2026 12:30 | 3 days | |
| 7 Mar 2026 00:00 | 10 Mar 2026 00:00 | 3 days | |
| 31 Jan 2026 00:30 | 2 Feb 2026 03:45 | 2 days | |
| 24 Jan 2026 00:00 | 26 Jan 2026 04:45 | 2 days | |
| 1 Jan 2026 05:15 | 7 Jan 2026 03:30 | 5 days | |
| 28 Dec 2025 03:00 | 31 Dec 2025 06:00 | 3 days | |
| 3 Dec 2025 07:45 | 6 Dec 2025 05:00 | 2 days |
A unit is stopped when its output falls to 2% of its maximum power or less (at least 5 MW); breaks shorter than an hour are merged. Maximum power is the highest output observed in the last 12 months. Scale: 7–13 days is a longer outage, 14–29 days a long one, 30 days or more a very long one.