Lignite unit

TUR 2-04

plant: Turów · operator: PGE GiEK
Power now
90 MW
Load
38% of 240 MW
Running without a break
4 days, since 14 Nov 2026

Last 24 hours

Unit output, MW, every 15 minutes
maximum power 240 MW
now 90 MW

Operating history

The selected period applies to the operating strip and daily energy: 20 Oct – 18 Nov 2026
All

Operation and stops

In operation on 5 of 30 days
stoppedrunning below 60% of max powerrunning at 60% or more

Daily energy

MWh per day. Select a day to see its profile.
selected day: Tuesday 17 Nov 2026 · 2,300 MWh

Day profile

Tuesday 17 Nov 2026, MW

Outages in the last 12 months

Lasting at least a day, most recent first
Time in operation
57.4%
Outages in total
154 days
StartEndLengthLabel
21 Jul 2026 09:4514 Nov 2026 02:15115 daysvery long outage
9 Jun 2026 00:3015 Jun 2026 13:456 days
21 May 2026 17:0026 May 2026 15:454 days
12 Mar 2026 23:3021 Mar 2026 04:008 dayslonger outage
21 Feb 2026 00:002 Mar 2026 15:459 dayslonger outage
16 Dec 2025 18:1525 Dec 2025 12:158 dayslonger outage
A unit is stopped when its output falls to 2% of its maximum power or less (at least 5 MW); breaks shorter than an hour are merged. Maximum power is the highest output observed in the last 12 months. Scale: 7–13 days is a longer outage, 14–29 days a long one, 30 days or more a very long one.